Posted On July 14, 2026

GDC greenlights $88M change order ahead of 2028 Hudson Tunnel boring

admin 0 comments
HHM Custom Homes LLC >> Uncategorized >> GDC greenlights $88M change order ahead of 2028 Hudson Tunnel boring

Kiewit subsidiary Weeks Marine is already mobilized in the Hudson River and expects to begin work on the change order later this year.